Trench support
Contents |
[edit] Introduction
A trench is defined as an excavation when its length greatly exceeds its depth. Shallow trenches are usually considered to be less than 6 m deep and deep trenches greater than 6 m. Depending on the dimensions of a trench, excavation can either be carried out by hand or using a mechanical digger. Trenches are commonly required to allow services, pipelines or foundations to be laid.
Water ingress into the trench is often a major issue and ground water table locations and soil strata should be investigated before any extensive excavation takes place.
Over short periods of time for relatively shallow depths most soil types will stand almost vertically without any problems. However, trenches other than those which are relatively shallow may require a trench support scheme.
[edit] Timber supports
Historically, trenching involved using timber to support horizontal and vertical soil loads and this technique is still used today. Timber trenching is generally used for low risk, narrow trenches, shafts or headings. The timber solutions require good workmanship and are reasonably labour-intensive, however they are versatile and the equipment required is easy to handle and transport.
[edit] Trench boxes
Trench boxes are suitable for low-risk situations in stable, dry ground and can be placed in pre-excavated trenches or installed using the ‘dig and push’ technique. The system requires at least two struts at each panel for stability which must be considered when access is required for construction work or piping.
For more information, see Trench box.
[edit] Trench sheets
Trench sheets are the most adaptable of the systems available, and are most commonly used to retain poorer soil. They can support deeper trenches with larger surcharges and provide a continuous support. They require multiple levels of strut support and the slenderness of the sheets can often limit the depth of the trench as they are installed by light machinery and could buckle under large vertical loads.
[edit] Related articles on Designing Buildings
- Backfilling.
- CDM.
- Crane supports.
- Demolition.
- Excavation.
- Facade retention.
- Falsework.
- Formwork.
- Health and Safety.
- Scaffolding.
- Shoring.
- Strut.
- Temporary works.
- Trench box.
- Trenching equipment.
- Tunnelling.
[edit] External references
- BS5975:2008 + A1: 2001 Code of Practice for Temporary Works Procedures and the Permissible Stress Design of Falsework (BSI 2011).
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
The heritage of nuclear and conventional power stations.
New measures to stop people being ripped off
Government to protect families from cowboy builders and aggressive bailiffs.
New Futurebuild showcase brings an innovation-first approach.
National Planning Policy Framework
Understanding the 2026 changes.
ECA's public affairs priorities
Member consultation opens to shape priorities for 2027 to 2030.
Dutyholder responsibilities from 1 July 2026.
Where performance meets practice
The Building Envelope Stage at UKCW Birmingham.
CIAT publishes briefing on planning reforms.
Leaders in Learning for Practice Network
Call for conservation leaders in learning to register interest in new network.
The importance of early engagement
Construction lessons from the Trillium HealthWorks Experience Centre.
Mayors are to be given planning call in powers
Mayors across England will be able to make the most important planning decisions.
The Master Builder: William Butterfield and his times. Book review.